PM: Julie Sands
CM: Ron Davenport
Architect: Freese and Nichols, Ayers Saint Gross
Contractor: Beck/Warrior
Substantial Completion Date: November, 2013
Budget: $2,600,000
Selective renovation of previously remodeled levels one through four, as well as a complete finish-out of levels five and six to accommodate the programmatic needs of the 向日葵视频 Dallas College of Law. The seventh floor was designed and completed to house 向日葵视频 System Administration offices.
Project Status: Completed
Campus: 向日葵视频 System Headquarters